The Capital Development Authority has sped up construction on the Margalla Avenue extension from the N-5 highway to the M-1 motorway and the Sangjani Interchange, with crews now working around the clock across several sections of the project. The authority says 43 per cent of the overall work is complete, a marked step forward from the 35 per cent reported earlier this month, and it has told its project teams to meet the construction deadline without compromising on quality.
The project is one of the most important road schemes under way in the capital. It extends Margalla Avenue by roughly 2.7 kilometres within the limits of Islamabad Capital Territory, starting from GT Road and running to the Sangjani Grid Station, where it will join a further 2.5-kilometre stretch being built by the National Highway Authority through Rawalpindi to connect with the M-1 motorway. Once finished, the link will give northern Islamabad direct access to the M-1, easing congestion on Kashmir Highway and 9th Avenue, and it will serve as a gateway for people travelling between Islamabad and Khyber Pakhtunkhwa, including those coming from Abbottabad, Mansehra and other cities. It will also make Islamabad International Airport easier to reach.
The pace of work has picked up noticeably in recent weeks. On November 9, the authority reported that 35 per cent of the project was complete, and by November 13 the figure had risen to 36 per cent. The jump to 43 per cent now suggests that the round-the-clock working ordered by the CDA chairman is beginning to show in the progress figures. The tendered cost of the project was Rs3.58 billion, and when the authority opened bids in March this year, construction firm New Khan Builders won the contract with a bid 10 per cent below that cost.
Underpass and Sangjani Interchange
At the Sangjani Interchange itself, the structural work is well advanced. Crews have finished the underpass structure, including its concrete walls and footing slabs, and at the interchange they have completed the piling and girder work. Steel reinforcement work is now under way, and the authority expects excavation to finish soon. The loops and ramps that will carry traffic on and off the interchange are in their final stages of construction, while work continues on the service road that runs alongside the main carriageway.
The interchange is the heart of the scheme. It is where the extended Margalla Avenue meets the existing road network, and its underpass, loops and ramps will decide how smoothly traffic flows once the road opens. Completing the heavy structural work first, the piling, the girders and the concrete walls, was the necessary foundation, and the steel fixing and excavation now under way are the steps that bring the structure towards completion.
N-5 Bridge and Airport Access
Work is also moving forward at the N-5 bridge, where crews have completed piling and excavation for the abutments on both sides. Four of the five culverts included in the project have been finished, and construction of the fifth is still under way. The bridge work matters because the N-5, the Grand Trunk Road, is one of the busiest highways in the country, and the new link must cross it cleanly if it is to carry traffic safely between Islamabad and the motorway network.
CDA Chairman Sohail Ashraf, who also serves as Chief Commissioner Islamabad, visited the construction site to review progress and directed the project teams to keep to the deadline while maintaining construction quality. He said the project would provide an important route into Islamabad for people travelling from other cities, particularly those coming from Khyber Pakhtunkhwa, and added that it would improve access to Islamabad International Airport for commuters travelling within and outside the capital.
The road has been a long time coming for the capital’s northern areas. Margalla Avenue was built to open up the sectors at the foot of the Margalla Hills, but without a proper link to the motorway network its usefulness was limited, and traffic heading for the M-1 or the airport had to funnel through already crowded routes. The extension and the Sangjani Interchange are meant to close that gap, giving the northern sectors and the towns of Khyber Pakhtunkhwa a direct route into the capital and a faster way to the airport, while taking traffic off Kashmir Highway and 9th Avenue, two of the roads that choke most often at rush hour.
There is still work to do before any of that can be felt. The fifth culvert remains unfinished, the excavation at the interchange has yet to be completed, and the service road and the loops and ramps are still being built. The National Highway Authority’s 2.5-kilometre stretch through Rawalpindi must also be finished before the link reaches the M-1. But with the heavy structural work largely done and the completion figure climbing from 35 to 43 per cent in a fortnight, the project has reached the stage where its finish is a matter of steady execution, and the test will then be whether it eases the congestion it was designed to relieve.